INTER PIPELINE COCHRANE EXTRACTION PLANT TURNAROUND

Client: Inter Pipeline

Timeline: February 2016 - June 2017

Project Value: $6.5 Million

Location: Cochrane Extraction Plant

PROJECT DESCRIPTION

➤ Supplied Turnaround Coordinator, scheduling, planning and logistics support for front end planning

➤ Developed communication strategy to ensure integration of all stakeholders 

➤ Developed and managed overall budget, integrated operations, project, maintenance schedule

➤ Managed all sub contractors 

➤ Managed and executed maintenance and small capitol welded projects 

➤ Supplied all supervision, labour, equipment and materials to conduct plant shut down and perform planned  regulatory and reliability inspections 

➤ D-490 Compressor Motor Swap 

➤ Moleseive Replacement in Dehy Towers 

PROJECT STATISTICS 

➤ 20,000+ Manhours 

➤ 0 LTI’s, 0 MA 

➤ 37 Internal Vessel Inspections 

➤ 6 Exchangers (3 Jetting Insitu, 3 Bundle Pulls) 

➤ 225 Relief Valves Serviced 

➤ Complete Re-tray of 2 De-ethanizer Towers