PROJECT – Suncor Bitumen Blending Manifold & UG Pipeline.
Manifold 2013:
▪ Receive, identify and manage supplied materials.
▪ Install piping and supports 12”-36” (weld, bolt, supports).
▪ Install 2 x 450 HP pumps (alignment, pipe stress).
▪ Complete tie-ins to below ground pipelines.
▪ Blast, coat and holiday test all underground and above ground pipelines.
▪ Install rock guard and fillcrete and critical areas.
▪ Hydrotest Manifold (remove valves, temp spools, pressure, drain, reinstate valves, pump base).
▪ Assist with commissioning (work along side Enbridge Operations).
▪ Install 4” UG drain piping and FRP run off tank.
Interconnecting Pipelines
▪ Install 12”-16” underground pipelines.
▪ Handle, string, weld, blast, coat, lower-in.
▪ Install risers and supports.
▪ Tie into the pig catchers.
▪ Hydrotest and pig 12” and 16” lines.