Client: CNOOC

Timeline: October 2021 - 2022 (In Progress)

Project Value: $85 Million

Location: AB HWY 881

PROJECT:

▪ 10 KM x 12” in 18” pipe in pipe underground pipeline.

▪ Anchors, Bulkheads and S Bends.

▪ 10km x 60M Wide Row.

▪ Heated Installation - Thermal expansion.

▪ Engineered Ditch.

▪ GPS machine controlled excavations.

▪ 4km x 36” & 42” crossing sleeves.

▪ Advanced leak detection.