Slurry Line Installation

Client: CNRL Horizon Sustaining Capital

Approx. value: $1.6 Million


This project involved the removal and installation of 21 Kilometres of piping and components ranging from 26" to 30". It followed the fabrication of the same piping completed just prior. The work was completed over the fall and winter months on a lump sum basis.

Services Provided